Modernization of patient rooms at the Langen Clinic
On behalf of Klinik Langen, we carried out a comprehensive modernization of the patient rooms on the third and fifth floors. The focus was on creating contemporary and functional rooms that meet today's requirements for modern patient care.
Scope of the work
The work began with extensive demolition work, during which floors, bathrooms, supply rails and the entire inventory were removed. A core part of the modernization was the installation of a new drywall with integrated supply rails. This was repainted together with all wall and ceiling surfaces after completion.
In terms of technical equipment, new electrical cables were laid and modern nurse call systems and fire alarms were installed. The bathrooms were fitted with new wall and floor tiles and contemporary sanitaryware. For a high-quality finish, the built-in cupboards and door frames were professionally painted, new floor coverings including skirting boards were laid and protective ram protection was installed.
Special challenges
A key challenge of the project was the tight schedule: Each room had a time window of just two weeks. However, thanks to precise planning and efficient coordination of all trades, this deadline was easily met. The technical complexity of integrating the existing sanitary pipes also required a particular degree of care and expertise. In addition, the work was carried out during ongoing hospital operations, which required precise coordination.
The result
The result of the modernization are modern patient rooms, which are characterized in particular by their multifunctional pre-wall installation and supply rail. The comprehensive refurbishment created contemporary rooms that meet the client's requirements.
At a glance
Refurbishment of the patient rooms:
- Demolition: Demolition of floor, bathroom, supply rail, inventory,
- Drywall construction: Production of drywall installation wall/ supply rail
- Floor: new floor covering + skirting board,
- Painting: Painting of the wall and ceiling surfaces, as well as the installation wall/supply rail
- Paintwork: Lacquered built-in cupboards, lacquered door frames
- Electrical work: Laying new electrical cables, nurse call, fire alarm
- Sanitary work: Wall and floor tiles, supply and fit/install new sanitaryware
- Carpentry work: Manufacture and install impact protection
Further projects

Complete modernization of a neurology practice

Seligenstadt Clinic - Neurological early rehabilitation (NFR) ward

Langen Clinic Patient rooms

Bergstrasse Ortho Center

Modernization project at the Seligenstadt clinic
chore - Quality is our foundation
Get in touch with us
+49 69 6066 4500
info@chore.de