RheinMain-Med
Conversion of a dental practice into a general practice
general contracting
Complete redesign of an existing practice on Hainer Weg
On behalf of the client, chore oversaw the complete conversion of the former dental practice on Hainer Weg into a modern medical care center (MVZ) for general practice—from demolition work through to handover, ready for operation.
client
RheinMain-Medlocation
Frankfurt am Main, Hesseindustry
Healthcare
Scope of the construction work
The renovation required a major overhaul of the existing structure, as the entire technical and spatial infrastructure had to be adapted to its new use. The renovation work was completed in about three months.
Demolition of existing structures
The project began with extensive demolition work, during which the specialized fixtures from the previous dental practice were systematically removed. In particular, the dismantling of the dental plumbing and electrical systems required a high degree of expertise: above all, the removal of the water lines, which was carried out with special care, not only to protect the existing structure but also to eliminate any health risks posed by stagnant water or contaminated sections of the piping.
Plumbing removal
Electrical dismantling
Grandfathering
Adjustment of the floor plan layout
The dental practice’s previous layout was not suitable for the needs of a medical care center. As part of the renovation, the floor plan was therefore completely redesigned: seven treatment rooms, a staff room, a laboratory, a reception area, and a waiting area were created based on a design concept that also takes hygiene requirements into account.
Floor plan layout
Land Use Planning
Usage Plan
Interior Finishes and Surfaces
After the demolition, the interior was completely rebuilt. Drywall and interior plastering work laid the foundation for the new room layouts. Tiles were installed in the relevant areas using materials that meet hygiene standards: low-grout installation, disinfectable surfaces, and wall tiles in all wet areas up to the required height.
Drywall construction
Interior plaster
Tiling
Spatial structure
Plumbing, Electrical Engineering, and Networking
The entire technical infrastructure was completely renovated during the renovation. New plumbing and electrical systems were designed to meet the needs of the medical care center and completely replace the previous dental-specific equipment. In addition, modern network technology was installed to support the center’s digital infrastructure.
Plumbing
Electrical installation
Dental Practice Technology
Fiber-optic connection
Since there was no fiber-optic connection in place prior to the renovation, a fiber-optic line was installed for the first time as part of the project. This laid an important foundation for the practice’s digital operations and ensured that the facility has a future-proof technical infrastructure.
Fiber optics
Network infrastructure
Digital Infrastructure
Specific Challenges and Potential Solutions
Land-use changes involving major interventions
01
Converting a dental practice into a general medical facility is no ordinary renovation project. Dental practices have a very specific technical infrastructure—from the water supply to the electrical wiring—that is designed for a completely different purpose. The complete demolition and subsequent new installation therefore required not only technical precision but also a deep understanding of the specific requirements of both types of practice.
Added to this was the challenge of redesigning the floor plan so that all areas necessary for the medical center’s operations could be arranged in a functional and efficient manner.
Tight schedule
Despite the extensive scope of work and the complexity of the change in use, all tasks were completed on schedule within approximately three months—thanks to structured project planning and the chore team’s well-coordinated processes.
02

Turning old stock into modern infrastructure
Now that the renovation is complete, the former dental practice has been transformed into a modern medical care center with a completely renovated and state-of-the-art technical infrastructure. With seven treatment rooms, a laboratory, a staff area, and an inviting reception and waiting area, the renovation creates the ideal conditions for the practice to operate smoothly—for both the medical staff and the patients.
From dismantling to handover, chore provided structured support at every step. We were able to focus on the opening because we no longer had to worry about the renovation.
Other healthcare projects
Discover more healthcare projects that we have successfully completed as an experienced partner in hospital and healthcare construction.
chore - Quality is our foundation
Get in touch with us
+49 69 6066 4500
info@chore.de